According to the terms of the contract with the owner, the prime contractor is responsible for what?

  1. Performance of all work

  2. Performance of only their own work

  3. Performance of subcontractor work

  4. Performance of the schedule

The correct answer is: Performance of all work

The prime contractor is responsible for the overall performance of all work described in the contract with the owner. This encompasses not just the tasks they personally execute, but also the work carried out by any subcontractors they may engage. The prime contractor serves as the main point of accountability for ensuring that the entire project meets the specifications, quality standards, and timelines set forth in the contract. This responsibility includes managing coordination among all parties involved, overseeing the integration of various components of the project, and ensuring that subcontractors fulfill their obligations. By taking on this comprehensive role, the prime contractor plays a crucial part in the project's success and is the primary representative in dealings with the owner, thereby bearing the ultimate responsibility for the project's performance and delivery.