Do contractors find value in allowing a higher proportion of overheads and fee for work completed early in the project?

  1. Yes, it motivates early completion

  2. No, they seldom see an advantage

  3. Only for large projects

  4. Yes, it reduces subsequent costs

The correct answer is: No, they seldom see an advantage

The perspective that contractors find little advantage in allowing a higher proportion of overheads and fee for early work completion stems from the financial implications tied to project management and cash flow. Contractors typically operate under a structured profit margin designed to account for risks and uncertainties throughout the entirety of a project. By not adjusting overheads and fees upwards for early completion, they maintain their established profit margins without incentivizing potentially premature completion that could lead to insufficient attention to quality or unanticipated issues that require additional time and resources. Moreover, the contractual agreements often specify the allocation of costs and profits over the duration of the project, and changing these terms mid-project could complicate financial forecasts and negotiations. Early completion, while appealing, does not necessarily translate into reduced overall project costs or improved profitability, especially if the primary aim is adherence to contract terms and effective resource allocation. Other viewpoints, like potentially reducing costs or motivating behavior, do not universally apply across all projects or contractor practices. Therefore, a conservative view on maintaining standard fee structures for early completion leads to the conclusion that contractors generally find no compelling advantage in adjusting overheads for work completed ahead of schedule.