Prepare for the Estimating Exam with our comprehensive quiz. Enhance your skills with targeted questions and detailed explanations. Excel in your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Estimating costs for non-standard masonry products is primarily the responsibility of whom?

  1. The homeowner

  2. The general contractor

  3. The subcontractor

  4. The architect

The correct answer is: The general contractor

Estimating costs for non-standard masonry products is mainly the responsibility of the general contractor because they oversee the entire construction project and coordinate different aspects of the work, including the procurement of materials. The general contractor has the expertise to assess the requirements of non-standard masonry products, taking into account the specific needs of the project, the marketplace, and the available suppliers. Additionally, since non-standard masonry products may not have set prices or established suppliers, it's crucial for the general contractor to source estimates that fit the unique characteristics and design of the project. They work closely with subcontractors, who handle the actual installation, but it is the general contractor who is ultimately responsible for integrating those costs into the overall project budget. While architects may design the project and provide specifications, their role is typically not focused on cost estimation but rather on ensuring that the aesthetic and functional aspects align with the owner's vision. Meanwhile, homeowners usually do not possess the necessary technical knowledge or market insight to estimate such specialized costs. Therefore, the general contractor serves as the primary point for estimating costs associated with non-standard masonry products.