Is the estimate-cost control process non-linear?

  1. True

  2. False

  3. Only in public projects

  4. Only for small projects

The correct answer is: False

The estimate-cost control process is generally considered linear because it involves a series of sequential steps that lead from initial estimation to final cost control. This process typically includes defining project scope, estimating costs, obtaining approvals, and monitoring expenses throughout the project lifecycle. Each step follows logically from the previous one, making the overall process predictable and consistent. In practice, while some complexities may arise, such as adjustments in response to unforeseen circumstances, these do not fundamentally change the linear nature of the process. The steps can often be revisited or refined, but they still adhere to a structured approach that enables project managers to maintain control over costs effectively. This characteristic is applicable regardless of the type or size of the project, debunking any notions that the process might vary significantly in public versus private initiatives or between large and small projects.