Practice this question and more.


What does a contractor aim to use whenever possible for backfill requirements?

  1. Imported fill material

  2. Material excavated at the site

  3. Specialty backfill products

  4. Chemically treated soil

The correct answer is: Material excavated at the site

A contractor aims to use material excavated at the site for backfill requirements whenever possible because this approach is typically more cost-effective and efficient. Utilizing on-site excavated material helps to reduce transportation costs and minimizes the need for importing additional fill, which can add to the overall expenses of a project. Moreover, it simplifies logistics and reduces the environmental impact associated with bringing in fill from off-site sources. Using excavated material also aligns with sustainable practices in construction, as it allows for the reuse of resources that are already present at the job site. By reusing soil or material that has been removed during excavation, contractors can streamline operations while adhering to best practices in resource management. While imported fill material, specialty backfill products, and chemically treated soil can have their specific applications, they typically involve higher costs and logistical challenges compared to reusing material already available on-site.