Which item may typically relate to masonry work but might not be included in a subtrade quote?

  1. Finishing work

  2. Temporary bracing masonry work

  3. Inspection fees

  4. Cleanup services

The correct answer is: Temporary bracing masonry work

The item that may typically relate to masonry work but might not be included in a subtrade quote is temporary bracing masonry work. This is because temporary bracing is often considered a site-specific requirement rather than a standard scope of work in masonry contracts. Masonry subcontractors usually focus on the installation and finishing of masonry itself, while temporary bracing is typically the responsibility of the general contractor or the main contractor managing the site. In contrast, items like finishing work, inspection fees, and cleanup services tend to be more directly associated with the overall masonry tasks and can often be accounted for in the subtrade quotation. Finishing work is a crucial part of masonry, as it includes sealing, plastering, or painting. Inspection fees relate to necessary compliance checks that often occur as part of the masonry work. Cleanup services are also commonly integrated into the scope of work to ensure the site is left orderly after the masonry is completed. Therefore, temporary bracing stands out as a specialized need that may not be commonly included in quotes from masonry subcontractors.