Prepare for the Estimating Exam with our comprehensive quiz. Enhance your skills with targeted questions and detailed explanations. Excel in your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is NOT a type of estimate?

  1. Detailed estimate

  2. Conceptual estimate

  3. Flat-rate estimate

  4. Rough estimate

The correct answer is: Flat-rate estimate

A flat-rate estimate is not typically categorized with the common types of estimates used in project management or cost estimation practices. Detailed estimates, conceptual estimates, and rough estimates are standard methods for calculating project costs, each serving different purposes and levels of detail. A detailed estimate involves a comprehensive breakdown of all costs associated with a project, often itemizing every component and labor requirement, leading to a precise total. Conceptual estimates provide a high-level overview and are usually drawn up early in the project lifecycle, often based on historical data or preliminary designs. Rough estimates offer a less precise projection of costs, typically used in the initial stages to gauge the feasibility of a project. A flat-rate estimate, however, is more of a pricing strategy used in certain services where a single fixed price is charged for a defined scope of work. This does not fit the categorization of estimating methods used to project costs in construction or similar projects. Therefore, the inclusion of a flat-rate estimate in this context indicates that it is not a recognized type of estimate compared to the others.